Skip to main content

Construction liens in Florida: a homeowner's overview

How Florida construction liens work: who can file a claim of lien, notice and deadline rules in Chapter 713, and steps homeowners can take before paying.

By AV Construction Group Corp. Published 8 min read

Illustration for articles about Florida permits

A construction lien is a legal claim that lets an unpaid contractor, subcontractor, or supplier ask a court to enforce payment against the property they improved. In Florida, a lien does not exist until a claim of lien is recorded, and people who did not contract directly with the owner must meet notice deadlines first. For homeowners, the practical risk is that paying your contractor in full does not always protect you if the contractor failed to pay others.

This is a general overview of Florida Statutes Chapter 713, not legal advice. Lien law is technical and deadlines are strict, so talk with a Florida attorney about a specific project or claim.

Who can claim a lien?

Section 713.01 defines a "lienor" as a contractor, subcontractor, sub-subcontractor, laborer, qualifying materialman, or professional lienor. Only these parties can hold a lien under the chapter. Roughly:

  • Contractor: contracts directly with the owner to improve the property.
  • Subcontractor or sub-subcontractor: works under the contractor or under another subcontractor.
  • Laborer: personally performs on-site work and does not supply materials or hire others.
  • Materialman (supplier): supplies materials, delivered to the site or specially made, without installing them.

A lienor with a direct contract with the owner (called "in privity") has a lien under section 713.05 for work under that contract. Subcontractors and suppliers not in privity have lien rights under section 713.06, but they must follow notice rules to keep them.

What is a claim of lien and when must it be filed?

The lien takes effect when a lienor records a claim of lien with the county Clerk. Section 713.08 says the claim must state, among other things:

  • The lienor's name and address for service
  • Whom the lienor contracted with
  • The labor, services, or materials furnished and their price or value
  • A legal description of the property and the owner's name
  • Dates of the first and last furnishing of labor or materials
  • The unpaid amount
  • For lienors not in privity with the owner, the date and method of serving the notice to owner

The claim must be sworn by the lienor or an agent who knows the facts. It may be recorded during the work or up to 90 days after the lienor's final furnishing of labor, services, or materials, and it must be served on the owner before recording or within 15 days after. The statute defines "final furnishing" as the last date of supply, which is not set by a certificate of occupancy or final completion. Fixing defects in earlier work does not extend it.

What is a Notice to Owner?

Subcontractors, suppliers, and other lienors who are not in direct contract with the owner, except laborers, must serve a notice to owner under section 713.06. The notice goes out before starting work or within 45 days after starting. The statute calls missing or late notice a complete defense to enforcement. The notice must carry a statutory warning, and homeowners who receive one are being told that the sender may look to the property for payment.

Section 713.18 lists how notices are served: hand delivery, certified or registered mail or other qualifying carriers, or posting at the job site if delivery cannot be completed.

How does the Notice of Commencement fit in?

The owner records a Notice of Commencement before work begins, and it identifies who should receive notices. The details are covered in Notice of Commencement in Florida.

Why can an owner be exposed after paying the contractor?

Section 713.06 sets the framework. In summary:

  • Before each non-final payment, the owner must pay lienors who have given notice, prorating if funds are short, and paid lienors should sign partial releases.
  • At final payment, the contractor must give the owner a final payment affidavit stating that lienors who served notice have been paid, or listing the unpaid lienors and amounts.
  • The owner must withhold final payment until the affidavit is delivered. A contractor who fails to provide it has no lien against the owner for that work.
  • If the owner pays improperly, the property can be liable to lienors up to the retained amounts plus the improper payments.
  • If an affidavit lists unpaid lienors, the owner may pay them after 10 days' written notice to the contractor and deduct those amounts from the contractor's balance.

When funds are short, the statute sets an order of priority: laborers, then other lienors, then the contractor. Consult an attorney before paying lienors directly or withholding funds.

What can homeowners do at a high level?

Statutes and Miami-Dade guidance point to several protective steps. They are not guarantees, and each project differs.

  1. Read the lien notice in your contract. For residential direct contracts over $2,500 with one to four dwelling units, section 713.015 requires a bold, capitalized warning, signed and dated by the owner, that unpaid workers and suppliers may have claims even if you paid the contractor. It advises requiring written lien releases and consulting an attorney.
  2. Ask who is working on the job. Miami-Dade says an owner can request a list of subcontractors and suppliers in writing by registered or certified mail, and the contractor has 10 days to provide it or may forfeit the right to lien the property.
  3. Record a Notice of Commencement and watch for Notice to Owner letters. County guidance advises requesting final releases from anyone who sent one.
  4. Use statutory releases. Section 713.20 sets progress and final payment waiver forms. Lien rights cannot be waived in advance, so a release should cover only work already paid for. A waiver can be conditional on a check clearing.
  5. Demand a sworn statement of account. Under section 713.16, an owner can demand a sworn account from a lienor, who has 30 days to respond or loses the lien.
  6. Confirm final inspections before the last payment. Miami-Dade advises getting proof of approved final inspections or a certificate of completion or occupancy, plus final lien releases.
  7. Consider a payment bond. Under section 713.23, a contractor can post a payment bond covering the contract price. Liens transfer to the bond and the owner receives an exemption from most lien provisions. The bond is attached to the Notice of Commencement.

What happens after a lien is recorded?

A lien does not last forever. Under section 713.22, a lien expires one year after the claim is recorded unless the lienor sues to enforce it within that year. The owner can record a Notice of Contest of Lien to shorten the enforcement window to 60 days after service. If the lienor does not sue in that time, the lien is extinguished.

Section 713.21 lists other ways to discharge a lien: a recorded satisfaction or release, failure to sue in time, a court order after a show-cause process, or a recorded judgment. A lien that knowingly inflates the amount or claims work not done is fraudulent under section 713.31 and unenforceable, but honest disputes over amounts do not count. These matters belong with an attorney.

Questions people ask

Can a subcontractor lien my home if I paid my contractor in full?

It can happen. A properly noticed and recorded lien can reach the property even when the owner paid the contractor, which is why statutes require the warning notice in residential contracts. Whether it applies to your situation depends on notices served and payments made.

Does a lien mean I lose my home?

The contract notice warns that a lien could lead to a forced sale, but enforcement requires a lawsuit and a court process. An attorney can explain the steps and options for your property.

Do lien rules apply to every job?

Section 713.02 exempts improvements with a direct contract price of $2,500 or less from most of the part, with limited exceptions.

What if I get a Notice to Owner?

Keep it. It means the sender may claim lien rights. Review it with your contract and payment records and ask your contractor to confirm payment status in writing.

Check before you decide

  • Does your contract contain the lien warning, and did you sign it?
  • Have you recorded the Notice of Commencement, and do you keep copies of every Notice to Owner?
  • Are you collecting releases that match the amounts actually paid?
  • Have you received a final payment affidavit before the final payment?
  • Do you have approved final inspections or a certificate of completion or occupancy?

See also how to hire a licensed general contractor in Florida. Statutes change, so verify current text and consult a Florida attorney.

Sources

  1. Florida Statutes s. 713.01 (2026)
  2. Florida Statutes s. 713.015 (2026)
  3. Florida Statutes s. 713.05 (2026)
  4. Florida Statutes s. 713.06 (2026)
  5. Florida Statutes s. 713.08 (2026)
  6. Florida Statutes s. 713.16 (2026)
  7. Florida Statutes s. 713.20 (2026)
  8. Florida Statutes s. 713.21 (2026)
  9. Florida Statutes s. 713.22 (2026)
  10. Florida Statutes s. 713.23 (2026)
  11. Florida Statutes s. 713.18 (2026)
  12. Florida Statutes s. 713.31 (2026)
  13. Miami-Dade County - Contractor and owner-builder responsibilities

Planning a project?

Tell AV Construction Group Corp. about your project and we will follow up.

Keep reading

More guides on the blog