In Miami-Dade County, a Certificate of Occupancy (CO) is issued for new construction, additions, remodeling, renovation, and changes of use. A Certificate of Completion (CC) is issued for standalone items such as fences and windows, and for shell buildings. Both are issued after the work passes final inspection and any completion holds are cleared, and both give owners a document showing the permitted work was finished.
This guide covers the county's process for unincorporated Miami-Dade. Cities run their own building departments, so the name of the certificate and the steps may differ. It is general information, not legal advice.
What is the difference between a CO and a CC?
The county describes both as confirming that work was completed in line with applicable codes. The difference is the type of project.
| Certificate | County describes it as | Examples the county gives |
|---|---|---|
| Certificate of Occupancy (CO) | Required for new construction, remodeling, renovation, and changes of use | New structure or addition, removing interior walls, converting a school into a restaurant |
| Certificate of Completion (CC) | Issued for standalone fences, windows, similar permits, and shell buildings | Fence, window replacement permit, shell building |
For smaller projects such as a fence, the county says no CO or CC is required, but you can request one. If you want a record that the work was finished, ask the permit counter whether you can request one.
Who needs which?
- Renovations, additions, new buildings, and changes of use: a CO.
- Standalone fences, windows, and shell buildings: a CC.
- Shell buildings: a CC after final inspection. Before a tenant opens, the space needs a CO through a building permit and then a Certificate of Use.
A Certificate of Use (CU) is a separate document from the zoning side. The county says a CO must be issued before a CU, and a CU confirms the business type is allowed in the zoning district and that the building meets zoning, environmental, fire, and building code requirements. A CU is required before opening a business in unincorporated Miami-Dade, and operating without one can lead to fines for both the business owner and the property owner. Businesses inside cities need a municipal certificate of use.
What are the requirements to get one?
The county lists three requirements: a fee, approved inspections, and all completion holds cleared. Fees are set in the county's building fee schedule.
Zoning final inspections can carry extra paperwork. The county's inspection page says they require a Landscape Certificate and a licensed surveyor's as-built survey. For projects using a private provider, a Certificate of Compliance must also be submitted once the final inspection is complete.
How does the process work?
- Pass the final inspection and clear completion holds. Your permit card lists the required inspections and any holds. Print it from the county's permit card page using your process number.
- Schedule inspections correctly. Request inspections by 4 p.m. one business day ahead, Monday through Friday, online, through the automated line at 305-591-7966, or through the Permit Counter at 786-315-2100. Inspections run 8 a.m. to 3:30 p.m.
- Check your status. Use the county's permit records menu to confirm that inspections and holds are cleared.
- Apply through the online CO/CC system. You can apply, print, or view the certificate there, and search certificate history by address, certificate number, or permit number.
- Pay the fees listed in the building fee schedule.
Re-inspection fees apply to each inspection beyond the initial one and one follow-up. The county also says all trade permits must be finalized before the certificate is issued, so an open plumbing, electrical, or mechanical permit can hold things up.
What is a temporary certificate?
A temporary certificate of occupancy or completion lets occupants use the space under set conditions for up to 90 days. The county says extensions are possible but need all trade and Fire approvals. You apply with the temporary certificate application form.
How do I close out a permit?
Closing a permit means finishing the final inspections so the record shows the work complete. A practical sequence:
- Confirm every trade permit tied to the job has a passed final.
- Resolve completion holds, including paperwork like surveys or compliance forms.
- Obtain the CO or CC, or at least proof the finals were approved.
- Make final payment to your contractor only after you have that proof. The county advises owners to confirm approvals with Permit Records at 786-315-2100 and to collect final lien releases first. See construction liens in Florida for homeowners.
- Keep copies of the certificate, final inspection records, and permits.
An open permit does not always disappear on its own. Section 553.79 lets any property owner close a permit, whether or not named on the application. The owner can keep the original contractor, hire another licensed contractor, or act as an owner-builder, and a replacement contractor is liable only for their own work. An expired permit that is substantially complete can be closed without a new permit. A local agency may close a permit six years after issuance without a final inspection if there are no apparent safety hazards, but the statute says "may." Arm's-length buyers cannot be denied permits or fined solely because a prior owner left a permit open. For more on expiration and reissuance, see Miami-Dade permit expiration, inspections and reissuance. For work done without a permit, see unpermitted work in Miami-Dade.
Questions people ask
Do I need a CO after a roof replacement?
The county page does not list roofing as an example for either certificate. Ask the permit counter what document closes your permit. The county says that before final payment you should have proof that final inspections were approved, or a certificate.
How do I check whether a certificate was already issued?
The county's online CO/CC system searches by address, certificate number, or permit number. For help, the Permit Section phone number is 786-315-2100.
Can I move in before the CO is issued?
The county describes a temporary certificate for up to 90 days under set conditions. Occupying without one is a question for the building department.
Who do I call?
The county lists the Herbert S. Saffir Permitting and Inspection Center at 11805 SW 26 Street, phone 786-315-2000. It also offers MeetQ for scheduling consultations.
Check before you decide
- Confirm whether your project needs a CO, a CC, or neither.
- Ask your contractor to list every trade permit and its final status.
- Check the permit card for holds before scheduling the last inspection.
- Hold final payment until you have approved finals or the certificate, plus lien releases.
- Save the certificate with your closing and insurance files.
For projects involving several trades, see remodeling and new construction. Rules and fees change, so confirm with the building department.