In Florida, anyone who excavates must notify Sunshine 811 at least two full business days before digging. Utility owners that belong to the system then mark their underground lines, and the excavator must hand-dig or use other careful methods within 24 inches of each mark. The rules are in Chapter 556 of the Florida Statutes, and breaking them can lead to citations and civil penalties.
What Sunshine 811 is
Sunshine 811, operated by Sunshine State One-Call of Florida, is the system that connects people who dig with the utilities that own buried lines. When you request a locate, called a ticket, member utilities are told about the planned dig and mark the approximate location of their underground facilities. The service is free. You can request a ticket by calling 811 or online.
Florida law requires the companies that provide service through underground facilities, such as gas, electric, communications, water and sewer operators, to be members. That is why one ticket reaches many utilities at once.
Who must call
The Sunshine 811 FAQ says anyone who is digging should call. The statute defines excavation broadly. It covers any man-made cut, cavity, trench or depression in the ground, and also includes pipe bursting, directional drilling and boring, and other trenchless methods. Demolition is covered too.
Contractors who dig for foundations, utility connections, drainage, sewer laterals, irrigation, fences, pools or site work should treat a ticket as a standard first step on every job.
Exemptions are narrow
Section 556.108 lists exemptions. Some examples:
- A single-family property owner digging entirely on their own land to a depth of 10 inches or less, with due care and without encroaching on a utility's right-of-way or easement
- Certain shallow work of 18 inches or less, such as hand-dug surveying or pest control work without mechanized equipment
- Some agricultural, railroad and industrial activity, if not on a marked right-of-way, easement or permitted use
- Hand-tool work by a member utility on its own facilities
If you are not sure that an exemption fits, call anyway. A ticket is free.
How the timing works
- Request the ticket at least two full business days before you dig. The statute allows ten full business days for work beneath state waters.
- Count carefully. The day you call does not count. A request made outside business hours is treated as received at the start of the next business day. Sunshine 811 describes day one as the day after you call.
- Utilities mark their facilities within the same two full business days.
- Wait for marks or responses. The excavator must stay out of the noticed area until facilities are marked, until the utility says none are present, or until the marking deadline passes, whichever comes first.
- Dig within the ticket window. The information given is valid for 30 calendar days. Temporary marks such as flags or stakes are also treated as valid for 30 days.
A rough example, assuming no holidays: a ticket requested on a Monday morning gives day one on Tuesday and day two on Wednesday, so the earliest start is generally Thursday. A Friday ticket moves everything to the following week. Always rely on the dates printed on your ticket.
A business day is Monday through Friday, excluding the holidays the statute lists, which include New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving and the Friday after, Christmas Eve and Christmas Day.
If a dig runs beyond 30 days, ask Sunshine 811 about updating the notice rather than relying on old marks.
What the marks mean and the tolerance zone
Utilities mark with paint, flags or stakes, using the Uniform Color Code of the American Public Works Association. White paint or stakes are used by the excavator to premark the planned dig area.
The tolerance zone is the area that extends 24 inches out from each outer side of a marked underground facility. Inside it, the excavator must use increased caution, such as hand digging, pot-holing, soft digging or vacuum excavation. Mechanized equipment in the zone must be supervised by the excavator.
Positive response: check before you dig
After you submit a ticket, each member utility returns a response. Sunshine 811 describes three outcomes:
- Marked. The utility has marked its lines. If you see no marks, verify the ticket details and contact the utility.
- Unmarked. The utility has facilities but has not marked them. Contact the utility.
- Clear. The utility says it has no facilities at the site. If you see meters, pedestals, transformers or know of lines nearby, contact the utility anyway.
Responses can change, so Sunshine 811 recommends checking them online rather than relying on an old email or printout. It also recommends photographing the site. For one response code, 2C, near a gas facility, the excavator must notify the gas operator of the start date and time first.
Private lines may not be marked
Sunshine 811 notes that some lines are private and may not appear in member responses. Not all utility owners locate privately owned lines such as the water and sewer pipes from the meter to a building. A "clear" response does not rule them out. Sunshine 811 points excavators to private utility locators for these.
Penalties and enforcement
- Failing to follow the rules, such as digging in the tolerance zone without care or not stopping when marks are gone, is a noncriminal infraction with a civil penalty of $500 plus court costs per infraction.
- Infractions involving pipelines carrying hazardous materials regulated by the federal pipeline safety agency carry $2,500 plus court costs.
- Knowingly removing or destroying valid markings is a second-degree misdemeanor.
- Citations may be issued by the State Fire Marshal or agents, fire chiefs, law enforcement officers and code enforcement officers, and they can order a stop to work.
The 2022 edition of the chapter also sets higher civil penalties of up to $50,000 for violations that cause an incident. Check the current edition of Section 556.116 before relying on any figure.
If you damage a line
Stop digging and notify the facility owner immediately, using the contact information on your ticket, even if damage seems minor. If natural gas or another hazardous substance is released, call 911 and leave the area. In a true emergency, such as a clear danger to life or property, the chapter's notice requirement may not apply to emergency excavation, as long as the system or operator is notified at the earliest opportunity and reasonable precautions are taken. The chapter does not allow a false emergency claim.
Questions people ask
Is calling 811 free?
Yes. Sunshine 811 says the service is free.
How long are marks good for?
Information given to the system is valid for 30 calendar days. Temporary markings are also treated as valid for 30 days.
Do I need to call to dig a shallow hole in my yard?
The statute exempts some owner work on a single-family property if it stays within 10 inches in depth, on your own land and clear of any utility right-of-way. Sunshine 811 advises calling for any digging. Calling is free and removes doubt.
Does 811 locate my private water or sewer line?
Not necessarily. Private lines may not be marked by the utilities. See sewer laterals in Miami-Dade for how those are handled.
Check before you decide
- Submit the ticket at least two full business days ahead.
- Check every utility's response online and compare it to the site.
- Premark the planned dig area in white.
- Hand-dig or vacuum excavate within 24 inches of marks.
- Keep the ticket number and photos on file.
- Arrange a private locator for lines the utilities do not mark.