Florida Product Approval and Miami-Dade NOA explained

What Florida Product Approval and a Miami-Dade Notice of Acceptance (NOA) are, how to check one, and why they matter for roofs, windows, doors, and shutters.

By AV Construction Group Corp. Published 6 min read

Illustration for articles about Florida permits

Florida Product Approval and a Miami-Dade Notice of Acceptance (NOA) are two ways of showing that a building product has been reviewed against the Florida Building Code. Florida Product Approval is the statewide system run under the Florida Building Commission. An NOA is Miami-Dade County's own approval, issued by its Product Control section. In Miami-Dade, which sits in the High-Velocity Hurricane Zone (HVHZ), roofing, windows, exterior doors, and shutters generally need approval before they can go on a building, and the county's roofing permit system accepts a current county NOA rather than a state approval.

What each approval is

Florida Product Approval

Section 553.842 of the Florida Statutes directs the Florida Building Commission to maintain a statewide product evaluation and approval system. Products that need approval under the code must be approved before use in construction. The statute names categories that must go through one of its approval methods, including panel walls, exterior doors, roofing, skylights, windows, shutters, impact protective systems, and certain structural components.

Approval can rest on several kinds of evidence, depending on the product: a certification mark or listing from an approved agency, a test report from an approved laboratory, an evaluation report from an approved entity, or a sealed report from a Florida-licensed engineer or architect. Independent third parties validate the evidence, and manufacturers must run quality assurance programs. Approved products are listed on the state's product approval database, part of the Florida Building Code Online site run by the Department of Business and Professional Regulation.

The statute also says products cannot be marketed as hurricane, windstorm, or wind-borne debris impact protection unless they are approved under the state system or a separate statutory route.

Miami-Dade Notice of Acceptance

The county describes an NOA as the document that shows a product or system is approved for construction in the county. It ties the manufacturer to the builder and carries the installation requirements. According to the county, exterior doors, windows, roofing, skylights, shutters, and structural components need one, as do items such as fences, railings, and screen enclosures.

The county's Product Control section reviews products, sets testing policy, and oversees quality assurance. Its application form says an NOA is valid for five years. A renewal filed before expiration also runs five years, and one filed after expiration is treated as a new application. The county audits manufacturers' quality assurance programs each year.

Why the HVHZ matters

The county explains that the High-Velocity Hurricane Zone covers Miami-Dade and Broward counties and has the strictest requirements in the Florida Building Code. Any product forming the outer envelope of a building, such as doors, shutters, windows, and truss plates, must have an approval before use there. The state statute does not mention the HVHZ in its text, so the zone's requirements come from the building code and the county's product control program.

The two systems connect. Miami-Dade's Product Control is one of the entities the statute recognizes to evaluate products, and the county says NOAs can be used to obtain Florida Product Approval for several product categories. That does not mean a state approval is accepted everywhere; the county's roofing system, for example, asks specifically for a county NOA.

What an NOA looks like

A typical NOA is a short document followed by drawings. The county's published example shows what to look for:

  • The issuer, which is the county's Regulatory and Economic Resources department, Product Control section.
  • An NOA number, an approval date, and an expiration date five years later.
  • A description of what is accepted, and the code edition it was reviewed against.
  • Sealed approval drawings that spell out dimensions, anchors, and installation details.
  • A requirement that each product carry a permanent label including the manufacturer's name or logo, the model or series, and the statement "Miami-Dade County Product Control Approved."
  • A statement that the complete NOA must be available at the job site when the building official asks for it.

The NOA becomes invalid when it expires or when the product's materials, use, or manufacture change.

Why it matters for each product type

  • Roofs. The county's roofing e-permitting guidelines say the system accepts only current Miami-Dade Product Control NOAs and rejects state approvals. For tile and shingle roofs, the application cannot advance without a valid NOA number. Inspection documents include the NOA for the roof assembly and for components such as tile adhesive or underlayment. See roof permit requirements in Miami-Dade.
  • Windows and doors. The county's fast-track disclosure form requires approvals for the current code and says expired approvals from an outdated code cycle are not accepted. It adds that when more than 25 percent of glazed openings are replaced, all replaced glazed openings must meet impact requirements, using impact glass or an approved impact device.
  • Shutters. The county says shutters need an approval and a separate permit, and inspectors check that HVHZ-approved shutters carry the proper markings.
  • Installation details. An NOA applies to the product as installed per its drawings. Field changes not supported by the approval documents require a revision before final approval, according to the county's window and door form.

How to check a product

  1. Get the NOA number or state approval number from the contractor's proposal or the product label.
  2. Search the county's product approval records by NOA number, or use the "Find a Product or Application" tool on the state's Florida Building Code Online site.
  3. Confirm the approval is not expired and matches the exact model, size, and installation option.
  4. Confirm it was written for the code edition in effect when you apply. The Ninth (2026) Edition takes effect December 31, 2026, and manufacturers could begin submitting approvals under it on July 1, 2026.
  5. Ask for a complete copy to keep at the job site.
  6. Check that the installed product carries the required label.

Questions people ask

Is a Florida Product Approval the same as an NOA?

No. They are separate approvals issued by different bodies. The county's roofing permit system, for example, accepts a county NOA and rejects a state approval. Ask the building department which one it requires for your permit.

What if my NOA expires during the project?

The county pages reviewed for this article do not say how an NOA that expires after permit issuance is treated. Ask the Permit Section before ordering materials, and keep a dated copy of the NOA that was current when you applied.

Who is responsible for checking the approval?

The permit applicant, usually the licensed contractor, enters and supplies the approval information, and inspectors compare the installed product with it. The sample NOA also says the manufacturer or its distributors must give the user a complete copy for the job site.

Check before you decide

  • Ask for the approval number for every roofing, window, door, and shutter product on your proposal.
  • Confirm the number, expiration date, and code edition.
  • Ask who will keep the complete approval on site.
  • Do not accept substitutions without a revised permit document.
  • Ask the building department what it requires before you sign.

Sources

  1. Florida Statutes s. 553.842 (2026) - Statewide product evaluation and approval
  2. Florida Building Code Online (DBPR) - Product Approval
  3. Florida Building Commission - 2026 product approval changes (9th Edition)
  4. Miami-Dade County - Construction materials and product control brochure
  5. Miami-Dade County - NOA application (renewals, validity, quality assurance)
  6. Miami-Dade County - Example Notice of Acceptance (NOA 26-0204.02)
  7. Miami-Dade County - Roofing e-permitting system guidelines
  8. Miami-Dade County - Fast-track window and door disclosure statement

Planning a project?

Tell AV Construction Group Corp. about your project and we will follow up.