Skip to main content

Public construction bonds: Miller Act and Florida law

Bid, performance and payment bonds on public construction: federal Miller Act thresholds, Florida's s. 255.05 bond rules, and the SBA Surety Bond Guarantee.

By AV Construction Group Corp. Published 7 min read

Illustration for articles about government contracting

Public construction owners usually require three bonds: a bid bond with the bid, then a performance bond and a payment bond once the contract is awarded. Federally, the Miller Act requires performance and payment bonds on construction contracts above a threshold that the FAR currently lists as $150,000. In Florida, section 255.05 requires a payment and performance bond on public construction, with exemptions for smaller contracts. The SBA Surety Bond Guarantee program can help eligible small businesses obtain bonds.

What the three bonds do

A bond is a three-party promise. The principal is the contractor. The obligee is the public owner. The surety is the company that stands behind the contractor's obligations. If the contractor defaults or fails to pay, the owner or claimants can look to the surety under the bond's terms.

  • Bid bond. Guarantees the bidder will sign the contract if awarded it and furnish the required performance and payment bonds.
  • Performance bond. Guarantees the work will be completed under the contract.
  • Payment bond. Guarantees that those who furnish labor, materials and supplies will be paid. The payment bond is the main route for subcontractors and suppliers to pursue unpaid amounts on a public project, which is why its claim rules matter.

Federal: the Miller Act and the FAR

The Miller Act is codified at 40 U.S.C. 3131 and implemented in FAR Subpart 28.1. The FAR tells contracting officers to require the following, according to the version of FAR 28.102 reviewed here:

  • Over $150,000 for construction: performance and payment bonds are required, with a waiver available for certain foreign work.
  • Over $35,000 up to $150,000: the contracting officer selects at least two alternative payment protections, such as a payment bond, an irrevocable letter of credit, an escrow arrangement or other security.
  • Amounts: the performance bond is generally 100% of the original contract price, plus 100% of increases. The payment bond is generally 100% of the price and not less than the performance bond.
  • Timing: bonds or alternatives must be provided before the notice to proceed or the start of work.

The statute's own text, as shown in the U.S. Code, refers to a $100,000 figure, while the FAR lists $150,000. The FAR is the regulation contracting officers follow, but because the two sources differ, verify the current figure in the solicitation and in FAR 28.102 before bidding.

Bid guarantees

Under FAR 28.101, a bid guarantee is required when a performance bond or a performance and payment bond is also required, unless the contracting office chief waives it. It must be at least 20% of the bid price and may not exceed $3 million. For construction it is normally a separate bid bond. In sealed bidding, a bid missing a required guarantee must be rejected unless a listed exception applies. A signed and dated power of attorney showing the signer's authority to bind the surety is part of what is checked.

Payment claims under the Miller Act

Under 40 U.S.C. 3133, a person who furnished labor or material and was not paid within 90 days after the last work or delivery may sue on the payment bond. A claimant who dealt only with a subcontractor must give written notice to the prime contractor within 90 days. Suit must be filed within one year after the last labor or material, in federal district court. These are notice-and-deadline rules, so anyone with an unpaid claim should read the statute and consult counsel promptly.

Florida: section 255.05, the "Little Miller Act"

Florida's public construction bond law is section 255.05 of the Florida Statutes, often called the Little Miller Act. The 2026 statutes show it was amended by chapter 2026-181, so use the current text. As written in the 2025 and 2026 statute pages:

  • Who is covered: contracts with the state, counties, cities, political subdivisions and other public authorities for building a public building, completing public work or repairing either.
  • When: the bond must be in place before work starts, or before work resumes after a default or abandonment.
  • Amount: generally equal to the contract price.
  • Recording: the bond must be recorded in the public records of the county where the project is located. The contractor must give the public entity a certified copy of the recorded bond before starting, and for contracts made on or after October 1, 2012 the public entity cannot pay the contractor until it does.
  • Exemptions: no bond is required for state contracts of $100,000 or less. Other public owners may, at their discretion, exempt contracts of $200,000 or less. The state may delegate authority to exempt contracts between $100,000 and $200,000.
  • Choice of surety: a public entity cannot require a particular agent or bonding company.
  • Alternatives: certain alternative security, such as cash or certain checks, can replace the bond.

Florida claim deadlines in brief

A claimant who is not in a direct contract with the contractor generally must serve a notice of intent to look to the bond within 45 days of starting work. A sworn notice of nonpayment may be served no earlier than 45 days after first furnishing labor or materials and no later than 90 days after the final furnishing. Suit generally must be filed within one year. Laborers are generally exempt from the notice step. A contractor can shorten the suit window by serving a contest notice. These deadlines are strict, and a claim can be lost by missing one. Get legal advice before relying on this summary.

Surety basics

A surety is a company that issues the bond after evaluating the contractor. SBA describes the surety's requirements as credit, capacity and character. The premium is the amount the surety charges, and it cannot exceed what the state insurance department authorizes. To compare options, ask a licensed surety agent what the underwriter will need from your business, how the premium is calculated, and what single-job and total bond limits would apply.

SBA Surety Bond Guarantee program

For small businesses that may not meet a surety's standard criteria, the SBA guarantees bid, performance, payment and ancillary bonds issued by participating surety companies. Per SBA's page:

  • Contract limits: up to $9 million for non-federal contracts and up to $14 million for federal contracts.
  • Fees: a 0.6% fee on the contract price for performance and payment bonds, paid to SBA. No fee for bid bonds.
  • Eligibility: the business must qualify as small under SBA size standards and still meet the surety's own credit, capacity and character requirements.
  • Guarantee percentage: under 13 CFR 115.31, SBA guarantees 90% of a loss when the contract is $100,000 or less, and for bonds for certain disadvantaged, HUBZone and veteran-owned small businesses. Otherwise the guarantee is 80%.
  • How to apply: through an authorized surety agency listed in SBA's database.

SBA guarantees the surety's loss, not the contractor's performance. The business still has to qualify with the surety. For size standards, see construction size standards and set-asides.

Questions people ask

Do I need a bond for every public job?

No. Smaller federal contracts may call for alternative payment protection rather than a bond, and Florida allows exemptions for lower-value contracts. The solicitation states what is required.

Who can claim on a payment bond?

People who furnish labor, materials or supplies on the project, subject to notice and deadline rules. The statutes above set those rules.

Does a bond mean the contractor is insured?

No. A bond is a guarantee to the owner and to unpaid claimants. It is different from an insurance policy that protects the contractor, so ask the surety how the arrangement works.

Check before you decide

  • Read the solicitation for bid guarantee, bond form, bond amount and deadline requirements.
  • Ask a licensed surety agent early. Underwriting can take time.
  • For Florida, confirm the current text of s. 255.05 and the owner's exemption policy.
  • If you are a subcontractor or supplier, calendar notice deadlines from your first day on site.
  • See /government and how procurement differs among federal, state and Miami-Dade buyers.

Sources

  1. Federal Acquisition Regulation, Subpart 28.1: Bonds and Other Financial Protections
  2. 40 U.S.C. 3131: Bonds of contractors of public buildings or works
  3. 40 U.S.C. 3133: Suits on payment bonds
  4. Florida Statutes, s. 255.05: Bond of contractor constructing public buildings (2026)
  5. Florida Statutes, s. 255.05 (2025)
  6. SBA: Surety bonds
  7. eCFR: 13 CFR Part 115, Surety Bond Guarantee