A change order is a written modification to a construction contract that changes the work, the price, the time, or some combination of them. On federal projects, the FAR Changes clause lets the contracting officer order changes within the general scope of the contract and requires an equitable adjustment when those changes affect cost or time. For many Florida local government contracts signed on or after July 1, 2025, state law sets a 35-day clock for the owner to act on a conforming change order price quote. This article is general information, not legal advice.
What a change order is
Public construction contracts are written before the work starts, and real projects rarely go exactly as planned. A change order is how the contract is updated. It may add work, delete work, change materials or methods, adjust the completion date, or settle a price for something that already happened. A change order only changes the contract if it is issued and signed as the contract requires. Verbal instructions, emails and site-meeting comments often do not qualify, which is where many disputes start.
Federal projects: the Changes clause
Federal fixed-price construction contracts over the simplified acquisition threshold include FAR 52.243-4, Changes. FAR 43.205 prescribes it, and a different clause, 52.243-5, applies to smaller construction jobs. Under 52.243-4:
- The contracting officer can issue a written change order, without notice to sureties, altering the drawings, designs or specifications, the method or manner of performance, government-furnished property or services, or the pace of performance. The change must be within the general scope of the contract.
- If a change raises or lowers the contractor's cost or the time needed, the contracting officer must make an equitable adjustment and modify the contract in writing.
- The contractor must assert its right to an adjustment in writing within 30 days after receiving the change order, and the clause lets the government extend that period. Agencies may vary the period under their own procedures, so read your contract.
- No adjustment proposal is allowed after final payment.
Directions that are not formal change orders
The clause also deals with oral or written directions, interpretations or other contracting officer actions that the contractor believes change the work. These count as changes only if the contractor gives written notice stating the date, circumstances and source of the order, and that the contractor regards it as a change. The clause says an adjustment does not cover costs incurred more than 20 days before that written notice. Other statements or conduct are not changes unless the clause says so. The practical lesson is to put it in writing promptly.
Types of change orders
The FAR does not use one list of change order types, but the structure in Subpart 43.2 helps:
- Unpriced change orders. The government issues the order first and the price is agreed later. These need two documents: the change order and a supplemental agreement for the equitable adjustment.
- Agreed-in-advance adjustments. The parties settle price and time first, and only a supplemental agreement is needed.
- Administrative changes and option exercises. These typically need one document.
Practitioners also talk about owner-directed changes, field conditions and design errors. Differing site conditions are covered by their own clause, FAR 52.236-2. It applies where subsurface or hidden physical conditions at the site materially differ from what the contract indicates, or where unusual unknown conditions differ from those ordinarily found. The contractor must give written notice promptly and before the conditions are disturbed, and the contracting officer must promptly investigate. No adjustment is allowed without the required notice unless the deadline was extended.
Pricing and documentation
FAR 43.204 says contracting officers should negotiate equitable adjustments in the shortest practicable time. It notes that contractor accounting systems are rarely built to separate changed-work costs, and it identifies the kinds of segregable direct costs, such as added distinct work and recurring labor and materials. It also says that a cost analysis should be made where appropriate. The agency can be asked to review the figures before agreeing.
Whatever the project, clear documentation tends to include:
- The written direction or request, with date and who gave it
- A description of exactly what changed and why
- Quantities, labor, materials, equipment and subcontractor quotes, kept separate from base contract work
- The effect on the schedule, if any
- The final signed modification
A federal supplemental agreement should state that all elements have been presented and resolved. FAR 43.204 says it should include a release of further claims arising from the same facts, with any agreed exceptions listed. Read that language carefully before signing.
Florida public works
Florida has no single change order statute for all public projects, and most terms come from the contract, the agency's procurement rules and the bid documents. One state rule is now clear: section 218.755, Florida Statutes, applies to contracts for construction services entered into on or after July 1, 2025 by a local governmental entity. When the entity receives a price quote for a change order it requested or issued, and the quote conforms to the statute and the contract, the entity must approve or deny it in writing within 35 days. A denial must identify the deficiencies and the actions needed to fix them. If the entity does not send a compliant notice, the quote is deemed approved, and the entity must pay the quoted amount on completion of the change order. A contract cannot alter the entity's duties under the section.
The statute does not define its key terms or set a dispute procedure, and it says nothing about when changed work may begin. Many public contracts require written authorization before changed work starts, and starting without it can put payment at risk. Also confirm whether the statute covers your project owner. The text refers to a "local governmental entity" without defining it, so ask the owner or an attorney how it applies to state agencies, state universities or projects with federal funds.
For the payment side of public work in Florida, see Florida prompt payment rules for public construction.
How change order disputes arise
Disputes usually come from a handful of causes:
- Work done on a verbal direction, then denied
- Late or missing written notice
- Disagreement on whether the work was already in the base scope
- Disagreement on price, markup or time
- Delay effects that were never priced
- A release signed on one change order that covers more than intended
On a federal contract, an unresolved disagreement goes through the Disputes clause, FAR 52.233-1. A contractor claim must be in writing and submitted to the contracting officer within six years after it accrues, and claims over $100,000 must be certified. The contracting officer issues a decision, which is final unless the contractor appeals or sues under 41 U.S.C. chapter 71. The contractor must keep performing while the dispute is pending. In Florida, dispute steps are in the contract, and deadlines can be strict.
Questions people ask
Can I perform the work before the change order is signed?
Read your contract. Many require written authorization first. On federal work, FAR 43.201 says the contractor must continue performing the changed contract once a change order is issued, and informal directions need written notice from the contractor to preserve a claim. Ask the contracting officer or an attorney before proceeding on an unclear direction.
Does a change order always increase the price?
No. A change can also reduce cost or time, and the adjustment goes in either direction.
Who decides whether a change is within scope?
At first, the owner's representative or contracting officer. If you disagree, the contract's dispute process applies.
Check before you decide
- Read the changes, notice, claims and dispute clauses before the project starts.
- Request written direction before changed work begins.
- Track changed-work costs in separate cost codes.
- Meet every notice deadline in writing.
- Read any release language in a signed modification.
- Ask a construction attorney before you sign a release or file a claim.