Florida's Local Government Prompt Payment Act sets deadlines for counties, cities, school boards and other local governments to pay construction contractors, and interest applies if they pay late. For construction, a payment request is generally due 20 business days after it is received, or 25 business days if an agent such as the project architect must approve it first. Contractors must then pay subcontractors within set days. This article is general information, not legal advice.
Who the rules cover
The Act is cited in statute as the "Local Government Prompt Payment Act" (s. 218.70). It covers a "local governmental entity", defined in s. 218.72 as a county or municipality, school board or district, authority, special taxing district or other political subdivision. A "contractor" is someone who contracts directly with that entity for construction services, meaning labor, services and materials to build, alter, repair, demolish or improve real property.
Separately, ss. 255.073 to 255.078 address timely payment, closeout and retainage on public construction contracts. Section 255.073 says that, apart from those sections, s. 215.422 governs timely payment, which covers state agencies. Which statute applies depends on the owner. Check the contract.
Payment deadlines for construction (s. 218.735)
Per the 2026 text:
- The local government must stamp each payment request with the date it is received.
- Payment is due 20 business days after the stamp date.
- If an agent must approve the request first, payment is due 25 business days after the stamp date.
- The local government must identify where requests are submitted within 10 days after contract award or notice to proceed.
- A request that does not meet the contract requirements must be rejected in writing within 20 business days, stating the deficiency and what is needed to fix it.
- A corrected request must be paid or rejected within 10 business days, or by the first business day after the next regular meeting if approval by ordinance, charter or other law is needed.
- If the contractor sends an overdue notice and the entity does not reject the request within 4 business days of delivery, the request is deemed accepted, except for any fraudulent or misleading portion.
A "proper" payment request or invoice is one that meets the statute and the entity's requirements stated in the project contract. Read the invoicing requirements closely, because a request that misses them can be rejected.
Interest on late payment
Section 218.735 provides that late construction payments accrue interest at 2 percent per month or the contract rate, whichever is greater. For other, non-construction purchases, s. 218.74 uses a different interest rule (1 percent per month, starting 30 days after the due date), so do not mix the two. Section 255.073 also states 2 percent per month for late construction payments by public entities.
Disputes and improper invoices
Undisputed portions of a request must still be paid on time. Disputes go through the procedure in the contract or ordinance, or s. 218.76(2) if there is none. That section sets 30 days to begin the entity's dispute procedure and 45 days for a final decision, and it lets a court decide the dispute afresh. In an action to recover amounts due under the Act, the court awards costs and reasonable attorney fees to the prevailing party. A contractor with a payment dispute should ask a construction attorney about the notice and timing steps.
Retainage
Retainage is money held back from progress payments until work is complete. Per s. 218.735 and s. 255.078:
- Public entities may withhold up to 5 percent of each progress payment, or less, and may reduce the rate on a schedule.
- The entity may release all or part of it at any time.
- If it pays retainage attributable to subcontractors or suppliers to the contractor, the contractor must remit it to them in a timely way.
- The 5 percent cap does not apply to federally funded construction where federal grantor requirements conflict.
- These retainage provisions do not apply if the total construction cost is $200,000 or less, so check the contract for retainage terms on smaller projects.
At closeout (ss. 218.735(7) and 255.077), the contract must call for a single list of unfinished items with estimated costs, developed within 30 calendar days after substantial completion for projects under $10 million. The entity then pays the balance, including retainage, within 20 business days, less 150 percent of the estimated cost to finish the listed items.
What subcontractors should know
- Pass-through timing. A contractor must pay its subcontractors and suppliers within 10 days after it receives payment from the local government. A subcontractor must pay its own lower-tier subcontractors and suppliers within 7 days after it is paid. Sections 218.735(6) and 255.073 state these timelines.
- Withholding. A party can withhold a disputed amount only after giving written notice of the amount and what is needed to cure.
- The Act's remedies run to the contractor. Section 218.72 defines "contractor" as the party that contracts directly with the entity. A subcontractor should not assume it can invoke the Act's dispute procedure directly. Its rights come from its subcontract and from other law, such as the payment bond on a public project (s. 255.05). See public construction bonds under the Miller Act and Florida law.
- Contract terms matter. Flow-down clauses in a subcontract can add or change procedures. See working as a subcontractor on public projects.
Federal projects for comparison
On federal construction contracts, FAR 52.232-27 sets payment of a progress payment within 14 days after the designated billing office receives a proper request, and it requires the prime to pay subcontractors within 7 days of receiving payment. Interest follows OMB rules, and the prime must include the clause's terms in subcontracts.
Questions people ask
Do business days include weekends?
No. The statute uses business days for owner payment deadlines and calendar days for some other periods, so read each deadline carefully.
Does the Act apply to a private project?
No. It covers purchases by local governmental entities. Private projects fall under other Florida law.
Does the 5 percent cap apply to my project?
Only if the project's total construction cost is above $200,000 and no federal grant conflict applies. The contract may set a lower rate.
Check before you invoice
- Identify the owner and which statute applies.
- Find the contract's invoice requirements and the designated place to submit.
- Calendar the stamp date and the 20 or 25 business day deadline.
- Know the retainage percentage and release terms.
- Confirm subcontract payment terms match the 10 and 7 day timelines.
Statutes are amended often, and this article reflects 2026 text available in October 2026. A construction attorney can advise on a specific payment dispute.