Florida condo milestone inspections and SIRS explained

What Florida law requires of condo boards for milestone inspections and structural integrity reserve studies: who is covered, deadlines, and board duties.

By AV Construction Group Corp. Published 8 min read

Illustration for articles about Florida permits

Florida requires condominium and cooperative buildings of three or more habitable stories to have a milestone inspection, a structural check by a licensed engineer or architect, by December 31 of the year the building turns 30, and every 10 years after that. Condo associations must also complete a structural integrity reserve study (SIRS) at least every 10 years and fund reserves for the structural and safety components it covers. Both rules grew out of the Surfside collapse and have been amended since, most recently in 2025 and 2026 session laws, so boards should confirm the current text with counsel.

This article summarizes statutes as they read on the Florida Legislature's website in October 2026. It is general information, not legal advice. Associations should work with an attorney and licensed design professionals.

Do these rules apply to your building?

Both rules are written for condominiums under chapter 718 and, for milestone inspections, cooperatives under chapter 719. The milestone statute covers buildings three or more habitable stories tall, measured by the Florida Building Code, and excludes single-, two-, three-, and four-family dwellings of three or fewer habitable stories. The SIRS rule likewise applies to each building three habitable stories or higher.

Neighborhood homeowners' associations that govern single-family communities are not the subject of these provisions as written. If your HOA's property includes a condominium building, that building is covered.

Milestone inspections: age, deadlines, and phases

When

The first inspection is due by December 31 of the year a building reaches 30 years, counted from its certificate of occupancy date. Repeat inspections are due every 10 years. The statute lets a local enforcement agency require the first inspection at 25 years when local conditions, such as proximity to salt water, call for it. A local agency can also extend a deadline for good cause if the owner has hired a professional and the work cannot reasonably be finished in time.

Miami-Dade has long run its own building recertification program, and it has integrated the state rules into it. The county's current page describes most buildings as recertified at 30 years and then every 10 years. For condo and co-op buildings of three or more stories within three miles of the coastline, it describes recertification at 25 years for buildings built in 1998 or later. Buildings from 1983 through 1997 in that coastal group, and other condo buildings from 1983 through 1992, were due by December 31, 2024, then every 10 years. Cities inside the county can apply different rules; the City of Doral, for example, states that the coastal 25-year rule does not apply there. Use the notice you receive from your own building department.

Who performs it

A licensed Florida architect or engineer performs the inspection, or leads a team as the design professional in responsible charge. In Miami-Dade, the county says structural and electrical reports must come from Florida-registered engineers or architects, and taller buildings generally need separate structural and electrical engineers.

Phase one and phase two

  • Phase one is a visual examination of habitable and non-habitable areas with a qualitative assessment of structural conditions. It is due within 180 days after owners receive the local agency's written notice. The inspector submits a sealed report to the local building official and gives it to the association.
  • Phase two is required only if phase one finds substantial structural deterioration. It can involve destructive or nondestructive testing, with test locations chosen to be as unobtrusive and easy to repair as practical. A progress report with a completion timeline is due to the local agency within 180 days after the phase one report is submitted.

The statute defines substantial structural deterioration as substantial structural distress or weakness that negatively affects the building's general structural condition. Surface issues such as cracks or peeling finishes do not count unless the engineer or architect finds they signal structural deterioration.

Local governments must adopt ordinances requiring repairs for substantial structural deterioration, and repairs must start within 365 days after the local agency receives the phase two report.

The structural integrity reserve study

A SIRS is a study of reserve funding for future major repairs and replacement of condominium property. Under section 718.112(2)(g):

  • It covers the roof, the structure (including load-bearing walls and primary structural members), fireproofing and fire protection systems, plumbing, electrical systems, waterproofing and exterior painting, and windows and exterior doors. It also covers any other item whose deferred maintenance or replacement cost exceeds $25,000, or the inflation-adjusted amount the state posts, whichever is greater.
  • It is based on a visual inspection performed or verified by a licensed engineer, a licensed architect, or a reserve specialist or professional reserve analyst certified by the Community Associations Institute or the Association of Professional Reserve Analysts.
  • It lists each inspected item with remaining useful life, estimated replacement cost or deferred maintenance expense, and a funding schedule.
  • It must be repeated at least every 10 years.

A design professional or licensed contractor who bids on the study must disclose in writing any intent to bid on the repair work that follows. The 2025 legislative analysis also describes a conflict-of-interest rule for people who perform a SIRS or milestone inspection and also provide repair services at the same property. Boards should read the current statute and ask their attorney how it applies.

Deadlines

For associations that existed on or before July 1, 2022 and are controlled by unit owners, the statute sets the first SIRS deadline at December 31, 2025. If a milestone inspection is due by December 31, 2026, the SIRS may be done together with it, but it may not be completed after December 31, 2026. A milestone inspection performed within the previous five years can substitute for the visual inspection part of the study. As of this writing, associations that have not completed a required study should speak with counsel promptly.

What boards must do

  • Arrange and pay for the inspection. The association arranges the milestone inspection and pays for the portions it maintains. Willful and knowing failure to have it done is a breach of fiduciary duty.
  • Notify owners. Within 14 days after receiving the local agency's written notice, notify owners of the requirement and the completion deadline.
  • Share the results. Within 45 days after receiving a milestone report, send the inspector's summary to every owner, post it conspicuously, and publish the full report and summary on the association's website if it has one.
  • Share the SIRS. Within 45 days of receiving the study, give owners a copy or a notice of availability and provide the state Division (DBPR) a statement that the study was completed. Officers and directors sign an affidavit acknowledging receipt.
  • Fund the reserves. For budgets adopted on or after December 31, 2024, an association required to have a SIRS cannot waive or reduce reserves for the covered components, and those reserve funds may be used only for them. Reserves can be funded through regular assessments, special assessments, lines of credit, or loans, with specific vote requirements. For budgets adopted through 2028, boards may pause reserve contributions for up to two consecutive budgets to fund milestone-recommended repairs, with majority approval of total voting interests.

The statute page reviewed lists a 2026 session law (chapter 2026-14) in its history. If your lawyer's summary predates 2026, ask whether anything changed.

Where permits fit

Repairs that come out of a milestone report or SIRS are construction work, so they generally need permits and licensed contractors like any other building project. See Miami-Dade building permit basics and how to hire a licensed general contractor in Florida.

Questions people ask

Is a milestone inspection the same as a SIRS?

No. A milestone inspection assesses the structural and life-safety condition of the building. A SIRS studies the reserve funding needed for specific components. They overlap, and the statute allows some coordination, but they have separate requirements.

Does the 40-year recertification still exist in Miami-Dade?

The county describes its program as recertification at 30 years and then every 10 years for most buildings, with buildings built on or before 1982 that already had an initial recertification keeping their schedule.

What happens if substantial structural deterioration is found?

The inspection moves to phase two, and local rules require repairs to begin within 365 days after the phase two report reaches the local agency. If repairs are not scheduled or started, the local agency must decide whether the building is unsafe for occupancy.

Check before you decide

  • Confirm your building's story count, certificate of occupancy date, and which local agency governs it.
  • Read the notice from the building department and calendar the 14-day, 45-day, and 180-day deadlines.
  • Verify the license of any engineer, architect, or reserve specialist you hire.
  • Ask about conflicts if the same firm may also bid on repairs.
  • Have the association attorney confirm current statutory text, including 2026 changes.

Sources

  1. Florida Statutes s. 553.899 - Mandatory structural inspections for condominium and cooperative buildings
  2. Florida Statutes s. 718.112 - Bylaws (reserves, SIRS, milestone inspection duties)
  3. Florida Statutes s. 718.103 - Definitions
  4. Florida House of Representatives bill analysis - CS/CS/HB 913 (2025)
  5. Miami-Dade County - Building recertification program
  6. City of Doral - Building recertification and milestone program