On a federal construction contract, the government generally owes an approved progress payment 14 days after the designated billing office receives a proper payment request. Final payment is generally due 30 days after the later of a proper invoice or government acceptance. If the government pays late on a proper request, interest is owed automatically. This article covers federal contracts under the Prompt Payment Act and FAR clause 52.232-27; it is general information, not legal advice.
Which rules apply to which project
Federal prompt payment is a separate system from Florida's. A federal contract uses the Prompt Payment Act (31 U.S.C. chapter 39) and FAR clauses. A county, city or school board project in Florida uses state law. For the Florida rules, see Florida prompt payment rules for public construction. Always check which clauses are in your own contract, since the contract controls.
The federal due dates for construction
According to FAR 52.232-27 and FAR 32.904, the main due dates are:
| Payment type | Due date |
|---|---|
| Progress payment | 14 days after the billing office receives a proper payment request |
| Retained amounts | As the contract states, or 30 days after the contracting officer approves release |
| Final payment | Later of 30 days after a proper invoice or 30 days after government acceptance |
If the office does not date-stamp the request when it arrives, the 14 days run from the date of the contractor's request, provided there is no disagreement over quantity, quality or compliance. The contracting officer may set a longer progress payment period with documented justification, and the Prompt Payment Act itself allows a solicitation to specify a longer period when the government needs time to inspect work. If a due date lands on a weekend or holiday, the government may pay the next working day without interest.
For interest purposes, the rules treat the government as accepting final work constructively seven days after the contractor completes it, unless actual acceptance happens sooner or there is a dispute. That rule is used only to compute interest. It does not require early acceptance or payment.
What makes an invoice "proper"
A payment request triggers the clock only if it is proper. FAR 52.232-27 lists what a proper invoice includes:
- Contractor name and address
- Invoice date and number
- Contract number, with order and line item numbers where applicable
- A description of the work performed
- Delivery and payment terms
- The name and address of the contractor official to receive payment
- The name, title, phone and mailing address of the person to notify about a defective invoice
- For progress payments, the substantiation and certification required by FAR 52.232-5
- A taxpayer identification number and electronic funds transfer banking information, where the contract requires them
- Anything else the contract requires
The progress payment certification
FAR 52.232-5 requires each progress payment request to include a certification, and the government will not pay without it. In summary, the contractor certifies that the amounts relate only to work performed under the contract, that earlier amounts owed to subcontractors and suppliers were paid, that timely payment will follow from the current payment, and that the request does not include amounts it plans to withhold from a subcontractor. The same clause requires the request to be backed by an itemization of work and by amounts for each subcontractor, including totals and prior payments.
Progress payments are generally based on estimates of work that meets the contract's standards and is approved by the contracting officer. Materials stored off site count only if the contract specifically allows it and the contractor shows title.
Defective invoices
The billing office must return an improper invoice within 7 days of receipt, with the reasons. If the notice is late, the office must adjust the due date when computing any interest. Because of this, accuracy at the start is cheaper than correcting later. Many agencies use electronic invoicing systems with their own steps, so follow the contract's instructions.
Interest on late payment
Under 31 U.S.C. 3902, an agency that fails to pay by the required date owes an interest penalty from the day after the due date through the day payment is made. The statute says the Secretary of the Treasury sets the rate and publishes it, so this article does not state a percentage; check the current published rate. Key points from FAR 52.232-27 and 32.907:
- Interest is paid automatically, without a request, when a proper invoice was received, required authorizing documentation was processed, and there is no dispute over quantity, quality, compliance or the progress payment amount.
- A late-payment notice must show the penalty amount, the rate and the period covered.
- Unpaid interest left over 30 days is added to principal, so later interest builds on the larger amount.
- An additional penalty may apply if the interest owed is $1 or more, it is not paid within 10 days after the invoice is paid, and the contractor sends a written demand postmarked within 40 days of payment. The demand must identify the invoice and state when the principal was received.
- No interest accrues on delays caused by disputes over amount or compliance, or on amounts the contract lets the government withhold.
- A temporary lack of funds does not excuse late payment.
Paying subcontractors on federal work
FAR 52.232-27 requires each subcontract to include a clause that the prime contractor will pay the subcontractor within 7 days of receiving payment from the government, along with an interest penalty clause. If a prime withholds from a subcontractor, it must give the subcontractor written notice, with a copy to the contracting officer, stating the amount, the reasons and the remedial actions needed. Once the problem is fixed, the withheld amount is due within 7 days, subject to the clause's conditions.
For how subcontractors fit into public work, see subcontractors on public projects in Florida.
Questions people ask
Is 14 days a guarantee of cash in the bank?
No. It is the due date after a proper request is received and approved. Review time, rejected invoices, disputes and withholding can delay payment, and the interest rules protect only proper, undisputed requests.
What if the government disputes part of an invoice?
The interest rules do not apply to delay caused by a disagreement over amount, quality or compliance. A dispute may need to be handled under the contract's Disputes clause, which involves the contracting officer's written decision. Ask a construction attorney about claim deadlines.
Do these rules cover state and local projects?
No. They apply to federal contracts that include the clause. State and local projects follow state law and local contract terms.
Check before you decide
- Confirm the clauses in your contract: 52.232-27, 52.232-5 and any agency invoicing instructions.
- Use a checklist for proper-invoice content before submitting.
- Keep proof of the date the billing office received each request.
- Make sure your subcontracts include the 7-day payment clause and the interest clause.
- Calendar the 7-day return window and 40-day written demand window.