How a federal construction bid works, start to award

The steps of a federal construction bid under sealed bidding: finding the notice, reading the solicitation, asking questions, submitting, opening and award.

By AV Construction Group Corp. Published 6 min read

Illustration for articles about government contracting

A federal construction bid typically runs in a fixed order: the agency announces the work, issues a solicitation with plans and specifications, answers questions through written amendments, receives sealed bids by a firm deadline, opens them publicly, and awards to the responsible bidder with the lowest responsive bid. Some federal construction is bought through negotiated proposals instead, so the solicitation tells you which method applies. This article describes the sealed-bid path at a high level, based on the Federal Acquisition Regulation (FAR).

Step 1: Find the opportunity

Formal federal solicitations are posted on SAM.gov, and you need an active registration to submit an offer. See SAM.gov registration for contractors. GSA also runs a forecast tool that lists upcoming contracts, often months before posting, and you can search it by keyword or NAICS code. GSA says forecasts are for planning only and do not commit the government to buy.

Under FAR 5.203, an agency generally publishes its notice at least 15 days before issuing a solicitation. For construction above the simplified acquisition threshold, FAR 36.213-2 calls for a presolicitation notice describing the work, its price range, location, tentative dates, how to get the plans, and whether the job is restricted to small businesses.

Notices state the size of the job as a range rather than a number. FAR 36.204 sets ranges from under $25,000 up to more than $10 million, and the government's own estimate is never disclosed.

Step 2: Read the solicitation

The invitation for bids (IFB) is normally organized in the FAR's uniform contract format. For federal construction, FAR 36.213-3 says the IFB includes items such as:

  • the wage determination
  • the estimated magnitude of the work and the performance period
  • how site inspection will be arranged
  • pre-bid conference details, if any
  • special instructions and reporting requirements

Read the NAICS code and any set-aside first, because they decide who may compete. Work covered by federal wage rules (Davis-Bacon) also brings payroll duties after award.

FAR 14.202-1 says that when a notice is required, bidding time must be at least 30 calendar days. That is a floor, so build your own schedule around the due date, including time to gather subcontractor and supplier quotes.

Step 3: Visit the site and ask questions

FAR 36.210 directs agencies to arrange site visits and data review for prospective offerors, to make significant site information available to everyone in the same way, and to keep a record of who attends. A pre-bid conference is optional under FAR 14.207, and the rule says it must never replace amending an unclear invitation.

That last point shapes how you ask questions. Under FAR 14.208, changes to the solicitation are made by written amendment, sent to everyone who received the invitation. Information given to one bidder must be shared with all when it is necessary or when its absence would prejudice others. An informal answer on a call is not the solicitation. Submit questions in writing by the date the IFB gives, then read every amendment before pricing.

Check how your solicitation wants amendments acknowledged. I could not read the acknowledgment provision itself, so follow the instructions in your IFB.

Step 4: Prepare the bid

Pricing is only part of the package. Check the IFB for:

  • Required forms and certifications. A missing material item can make a bid non-responsive. See responsive vs responsible bidders.
  • A bid guarantee. Under FAR 28.101-1, an agency generally requires one when it requires a performance bond or a performance and payment bond. FAR 28.101-2 sets the guarantee at no less than 20 percent of the bid price, capped at $3 million. Under FAR 28.101-4, a missing required guarantee leads to rejection in sealed bidding unless a listed exception applies. See public construction bonds.
  • Surety paperwork. FAR 28.101-3 treats a missing signed power of attorney at bid opening as a responsiveness problem.

Step 5: Submit on time

Bids must arrive at the office named in the solicitation by the exact opening time (FAR 14.302). Electronic bids count only if the solicitation permits that method (FAR 14.301(d)). If the IFB sets no time, the default deadline is 4:30 p.m. local time on the due date. You may modify or withdraw a bid before the deadline by a method the solicitation allows.

Late bids are narrowly handled. Under FAR 14.304, a late bid is considered only if it arrives before award, would not unduly delay the acquisition, and meets specific proof-of-timely-receipt conditions. Do not plan around exceptions.

Step 6: Bid opening

The agency opens bids publicly and records them, reading them aloud when practical (FAR 14.402-1). The abstract of offers is generally public. Opening shows the prices, but it does not decide the award.

Step 7: Review and award

Before award, the contracting officer examines bids for mistakes and asks for verification when one is apparent or suspected (FAR 14.407). Obvious clerical errors may be corrected after the bidder confirms its intent, and other corrections face a high bar. The officer also checks that prices are reasonable and not materially unbalanced and makes a responsibility determination (FAR 14.408-2).

Award goes to the responsible bidder whose conforming bid is most advantageous, considering price and price-related factors (FAR 14.408-1). The notice of award for construction requires prompt execution of payment and performance bonds and gives the work start date or says a notice to proceed will follow (FAR 36.213-4). Unsuccessful bidders are notified within three days after award (FAR 14.409-1). Protest rights are governed by FAR Subpart 33.1, which I did not review. Ask counsel about deadlines.

Questions people ask

Does the lowest bid always win?

No. The lowest bid must also be responsive and from a responsible bidder. Federal rules also allow rejecting an unreasonably priced or materially unbalanced bid.

Is every federal construction job sealed bid?

No. The IFB in this article is the sealed-bid method. Agencies can also use negotiated procurement for construction. Compare IFB, RFP and RFQ.

Can I bid without bonding capacity?

If the solicitation requires a bid guarantee and bonds, you need them. Talk to a surety early. Smaller federal jobs may carry different payment protections, which the solicitation will spell out.

Check before you decide

  1. Confirm SAM.gov registration is active and will stay active through award.
  2. Read the NAICS code, set-aside, wage determination and bonding requirements.
  3. Attend or review the site visit materials.
  4. Send questions in writing and read every amendment.
  5. Check forms, bid guarantee and signature requirements the day before.
  6. Arrive early at the submission point the IFB names.

Federal rules change and each solicitation can modify them. Rely on the solicitation text and ask the contracting officer or an attorney about anything unclear.

Sources

  1. FAR 5.203: Publicizing and response time
  2. Federal Acquisition Regulation, Subpart 36.2: Special aspects of contracting for construction
  3. Federal Acquisition Regulation, Subpart 14.2: Solicitation of bids
  4. Federal Acquisition Regulation, Subpart 14.3: Submission of bids
  5. Federal Acquisition Regulation, Subpart 14.4: Opening of bids and award of contract
  6. Federal Acquisition Regulation, Subpart 28.1: Bonds and other financial protections
  7. GSA: Find federal contract opportunities