In Miami-Dade, a window or exterior door must have an approved Notice of Acceptance (NOA) or Florida Product Approval for the current code, and replacing one needs a building permit. An impact-rated product is one tested against flying debris and then repeated wind-pressure cycles. The approval, the product label and the installation inspection fit together, and each is something you can check yourself.
What "impact" means
Miami-Dade sits in the High-Velocity Hurricane Zone (HVHZ), which the county describes as having the most stringent requirements in the Florida Building Code. Products in the building envelope, including windows, exterior doors and shutters, require an approval before they can be used on a building there.
The HVHZ impact test is TAS 201. Intertek's summary of it describes two missile types:
- Large missile. A nominal 2x4 timber weighing 9 pounds, fired from an air cannon at 50 feet per second (80 for some higher-risk buildings).
- Small missile. Steel balls of about 2 grams and 5/16 inch in diameter, fired at 130 feet per second.
After the impacts, the specimen goes through cyclic pressure loading, which simulates wind gusts pushing and pulling on the unit. A companion standard, TAS 202, covers air infiltration, water resistance, static pressure and forced entry, and TAS 203 covers the cyclic loading.
Which level goes where
An Intertek engineer's presentation to the National Glass Association says large-missile protection applies within 30 feet of the ground, while small-missile protection applies above that. A Florida Building Commission staff analysis quotes older code text to the same effect. Because the exact trigger can be framed differently in different code editions, ask your contractor and the building department which missile level applies to each opening on your house. An opening high above the ground, such as on the upper floors of a tall building, may be rated differently from one near grade.
Not every window is impact-rated
Notices of Acceptance include a line for the missile impact rating. Two example NOAs for aluminum windows, one for a horizontal rolling window and one for a single hung window, list that rating as "None." Another example, a horizontal sliding window, is rated small missile only. A product can be NOA-approved yet not suitable for an opening that needs large-missile protection. Read the rating on the NOA, not just the word "approved."
The permit process
Who can pull the permit
Miami-Dade's permit page says permits are issued in the name of the person doing the work, and only licensed contractors or owner-builders may obtain one. Replacing windows and doors counts as exterior repair work that needs a permit. The county's licensing brochure says working without the right license violates county code and Florida Statutes Chapter 489. For license checking, see how to hire a licensed contractor in Florida.
The fast-track option
For single-family homes, duplexes and townhouses with a mean roof height of 30 feet or less, the county offers a fast-track permit for exact changeouts of windows or doors. The disclosure statement the county publishes says:
- It covers like-for-like replacement of existing openings only. Modifying, adding or deleting openings is not allowed.
- Owner and contractor both sign notarized, sworn statements, and applications may be audited. Erroneous applications can lead to revocation and repayment of fees.
- Product approvals must be for the current building code. Expired approvals from an earlier code cycle are not acceptable.
- If more than 25 percent of a building's glazed openings are replaced, all replaced openings must be impact-resistant, using impact glass or an approved impact device. The form cites Section 707.4 of the Existing Building volume.
- Shutters and other impact devices need a separate permit application.
- If the work exceeds 30 percent of the building's assessed value, residential energy code requirements also apply.
- Bedroom windows must still provide emergency escape and rescue openings.
The county's general permit page adds that a Notice of Commencement is required before inspections when the work value exceeds $5,000, signed by the owner and recorded. Confirm current thresholds when you apply.
Code edition timing
The Ninth Edition (2026) Florida Building Code takes effect December 31, 2026. Miami-Dade says applications on or after that date, and portal submissions after 4 p.m. on December 30, 2026, must follow the new edition. Approvals should match the edition in force for your application. For how approvals work generally, see Florida Product Approval and Miami-Dade NOA explained.
Installation and inspection
An impact window performs as tested only if it is installed the way its approval drawings require, since test units include the frame and anchors. The glass association presentation notes that tested fasteners match the size and spacing used in the field. Your installer should work from the NOA drawings.
Under the fast-track process, windows get a "102-Buck and Fastener" inspection, requested online by the contractor after all windows are installed and before the interior perimeter is caulked, sealed or finished. It is the final inspection and closes the permit. Standalone doors get a final inspection at the same point. The county asks contractors not to install fastener cover plates that would hide the fasteners before the inspection. Field changes that the approved documents do not support need a revision. Other permit types may involve different inspections, so ask what yours requires.
How to verify a product label
Each NOA states a label requirement. The examples reviewed say each unit must carry a permanent label with the manufacturer's name or logo, city and state, the model or series, and the statement "Miami-Dade County Product Control Approved," unless the NOA says otherwise. To check:
- Find the permanent label on the unit and read the manufacturer, series and model. Ask your installer to show it to you before the frame is finished.
- Get the NOA number from the proposal or permit and look it up through the county's product control records.
- Match the series, size, glazing and installation option on the NOA to what is on site.
- Check the expiration date printed on the NOA, and confirm it was valid when your permit was applied for.
- Confirm the missile rating covers the opening's height and location.
- Keep a copy of the full NOA with the permit documents.
Questions people ask
Do I need a permit to replace one window?
Miami-Dade's permit page lists window and door replacement as work requiring a permit. A single-window project is still covered, and the 25 percent rule applies when you replace more.
Can I use a Florida Product Approval instead of an NOA?
The county's fast-track form accepts either, if current for the code. Ask the building department which one your permit type accepts.
Do shutters need a permit too?
Yes, the county says shutters and other impact devices need a separate application, and approved shutters should be properly marked.
Check before you decide
- Ask for the NOA or approval number for every window and door.
- Check the missile rating and expiration against each opening.
- Ask who pulls the permit and schedules the buck and fastener inspection.
- Do not let anyone seal the frame perimeter before the inspection.
- Keep the NOA, permit and inspection records.
See general contracting and remodeling and new construction.