Miami-Dade's published rule is that a building permit gives you 180 days to complete work and call for inspections, and each approved inspection extends the permit another 180 days from the approval date. A permit that sees no approved inspection within that window can become null and void. A new state law that took effect July 1, 2026 changes the starting period for single-family dwelling permits, so confirm the period printed on your own permit.
The details below describe unincorporated Miami-Dade County. Cities in the county run their own building departments and may use different procedures.
How long a permit stays valid
The county's application page says the clock is 180 days after issuance. An approved inspection on the master permit, or on any sub-permit, extends the permit for another 180 days from the date of approval. The county's guide for new permit holders adds that a permit is null and void if work has not started within 180 days of issuance, or if work is suspended or abandoned for 180 days. Work counts as active when there is an approved inspection inside that window.
The July 2026 state change
House Bill 803 amended the permit-expiration language in Florida law, effective July 1, 2026. Section 553.79 now says a permit for a single-family dwelling expires one year after issuance, or on the effective date of the next Florida Building Code edition, whichever is later. It also lets a local government email or mail the owner and the listed contractor a written expiration notice at least 30 days beforehand, and it confirms that local governments may extend permits.
The county's June 30, 2026 advisory memo says the one-year period applies only to the initial validity period before work has occurred, and that the 180-day extension after each approved inspection continues to apply. The memo also says the Florida Building Commission is expected to issue a code supplement on the topic later in 2026. Because the county's own pages still describe 180 days, ask the Permit Section which period applies to your permit.
Declared emergencies can also change deadlines. The memo notes that an executive order under section 252.363 of the statutes may extend expiration dates.
The inspection sequence
The county does not publish one universal sequence for all work. The order depends on the permit type, and the basic rule is that inspectors must see the work before it is covered or concealed. Examples from the county's own roof checklist show how this works:
| Roof type | Inspections in order |
|---|---|
| Asphalt shingles | Installation, before the anchor sheet is covered, final |
| Metal panels | Installation, final |
| Tile | Before the anchor sheet is covered, during cap sheet installation, tile placement, final |
| Built-up roofing | Before the anchor sheet is covered, final |
For window replacements under the county's fast-track process, a "buck and fastener" inspection happens before the interior frame is sealed or finished. Fasteners cannot be hidden under cover plates until that inspection passes. The details of roofing inspections are covered in roof permit requirements in Miami-Dade.
How to schedule
According to the county, you request inspections one business day ahead, before 4 p.m., Monday through Friday, online or by phone. You need the permit number and the three-digit inspection code from the permit card. Keep the stamped, approved plans and the permit card on site. The first re-inspection after a failed inspection is included; later ones carry a fee. Some inspections can be done by video call.
The final inspection and completion
When the last inspection passes, the project can move to a Certificate of Occupancy or Certificate of Completion, depending on the work. The county says all trade permits must be finalized and any completion holds cleared first. Temporary certificates can be granted for up to 90 days, with extensions possible.
The county advises owners not to make final payment until they have proof that final inspections were approved, or a Certificate of Completion or Occupancy, and final lien releases from suppliers and subcontractors.
What happens when a permit expires or is abandoned
The county page describes the process briefly: for an expired permit, choose "Permit Reissuance" in the online portal. A "Permit Extension" application type also exists. The page does not state deadlines or criteria for either, so ask the Permit Section at 786-315-2100.
Several facts from other sources can help you plan:
- State law lets owners close permits. Under section 553.79(16), the owner may finish and close a permit by hiring the original contractor, hiring a different licensed contractor, or acting as an owner-builder. A replacement contractor is not liable for the first contractor's defects. See owner-builder rules in Florida.
- Substantially complete expired permits can be closed. The statute lets a local agency close an expired permit without a new permit if it determines the work was substantially completed. The code in effect when the application was received generally governs, unless an alternative was approved.
- Six-year closure is discretionary. A local agency may close a permit six years after issuance without a final inspection if it finds no apparent safety hazards. The statute says "may," and it does not describe a process.
- Fees can be partly credited. The county fee schedule (effective October 1, 2022) gives a 50 percent credit of the permit fee for a re-application on the same project if filed within six months of a permit becoming null and void. Fee schedules are updated, so check the current one.
An open or expired permit does not go away by itself, and the county lets anyone search for open, unfinalized permits by address or folio number. That is one way unpermitted and unfinished work can surface later.
Which code applies after a long delay
Miami-Dade's notice says the Ninth (2026) Edition of the Florida Building Code takes effect December 31, 2026. Applications and plans submitted on or after that date must comply with it, with a portal cutoff of 4 p.m. on December 30, 2026. Expired applications (not issued permits) filed before the cutoff can request an extension within 180 days of expiration, in writing, showing good-faith pursuit. Those that do not qualify need a new process number, fees, and plans meeting the 2026 edition.
Questions people ask
Does an inspection really extend my permit?
According to the county, an approved inspection on the master permit or any sub-permit extends the permit for 180 days from the approval date. The county's wording refers to an approved inspection, so ask the Permit Section how it treats a failed one.
Who gets the expiration notice?
State law lets a local government send a written notice to the owner and the listed contractor at least 30 days before expiration. It says "may," so do not rely on receiving one.
Can my permit be cancelled?
The county fee schedule lists a cancellation fee for expired permits, charged per review or required inspection. Ask the Permit Section about cancellation if no work has started.
Check before you decide
- Read the dates on the permit card and note the next deadline.
- Schedule each inspection before the work is covered.
- Keep copies of approved inspection results.
- If a contractor leaves, ask about reissuance or a change of contractor before the permit lapses.
- Confirm which code edition applies to any new application after December 30, 2026.