Florida law lets a property owner act as their own contractor on certain projects without a contractor license, but only under conditions. The owner must personally supervise the work on site, the building must be for the owner's own use rather than for sale or lease, and the owner becomes the responsible party of record on the permit. The exemption removes the license requirement for the owner. It does not remove the building code, the inspections, or the owner's obligations to workers.
This article is general information, not legal advice. Statutes and county forms change, so confirm current requirements with the building department that will issue your permit.
What the owner-builder exemption covers
The exemption sits in section 489.103(7) of the Florida Statutes. The 2026 text of the statute describes four situations:
- New construction or improvements. An owner may build or improve a farm outbuilding, a one- or two-family residence, or a commercial building costing no more than $75,000. The structure must be for the owner's own occupancy or use, not offered for sale or lease.
- Disaster roof repair. An owner may repair or replace wood shakes or asphalt or fiberglass shingles on a one-, two-, or three-family residence damaged in a disaster covered by a gubernatorial executive order, again with a limit on selling within a year.
- Solar panels. An owner may install, remove, or replace solar panels on a one- to three-family residence where the local permitting agency takes part in a specified U.S. Department of Energy grant program. Licensed electrical contractors must handle the wiring and interconnection.
- Finishing an open permit. An owner may complete a permit after a listed contractor substantially completed the project, if the local permitting agency approves. This applies to one- and two-family homes, townhomes, accessory structures, and individual residential condominium or cooperative units.
Electrical work has its own parallel exemption in section 489.503(6), with the same owner-use theme and the same $75,000 commercial cap.
The one-year sale presumption
If an owner sells, leases, or offers to sell or lease the structure within one year after completion, the statute treats that as creating a presumption that the owner built it for sale or lease. That presumption can be used against the owner in an enforcement action. The exemption is meant for owners building for themselves, not for people building to sell.
One thing to watch: Miami-Dade's owner-builder instruction sheet, revised April 2021, describes a 24-month period and a smaller commercial category than the current statute. The statute is the law; ask the county which period it applies when you apply. For the wider permit process, see Miami-Dade building permit basics.
The disclosure statement
Before a permit is issued, the owner must personally appear, sign the application, and receive a written disclosure statement. The statute sets out twelve points. In plain terms, the statement tells the owner:
- Florida requires contractors to be licensed, and the owner is using an exemption.
- The owner is the responsible party of record and can reduce financial risk by hiring a licensed contractor and filing the permit in that contractor's name.
- The owner must directly supervise the construction on site.
- The owner may not hire an unlicensed person to act as contractor or to supervise workers.
- The owner may not delegate supervision to a licensed person who is not licensed for that kind of work.
- Anyone unlicensed who works on the project must be the owner's employee, which means withholding federal income tax and Social Security contributions and providing workers' compensation.
- The owner may be liable for injuries to unlicensed workers, and homeowner's insurance may not cover them.
- The work must comply with applicable laws, building codes, ordinances, and zoning rules.
- The owner must verify the license of any contractor hired.
Miami-Dade's form adds items such as proof of ownership (a recorded deed or a county tax receipt), identity verification, and a notarized signature. The county sheet also says the owner must keep the knowledge of the Florida Building Code needed for the work and must tell the county about any change to the information provided.
What owners remain responsible for
Choosing the exemption shifts responsibilities to the owner that a contractor would normally carry:
- Permits for each trade. The county instructions say electrical, plumbing, mechanical, roofing, and septic abandonment work need separate permits. Some trades may require a licensed contractor even when the owner holds the main permit.
- Inspections. The owner arranges inspections and must keep the approved plans on site. See how permit validity and inspections work in Miami-Dade.
- The Notice of Commencement. The county advises owners to record one with the Clerk of Court for improvements over $2,500, to sign it personally, and to post a copy at the site.
- Workers. The owner is the employer of anyone working without a license, with the tax, payroll, and workers' compensation duties that follow.
- Final payment and lien releases. The county advises getting proof of approved final inspections, or a Certificate of Completion or Occupancy, and final lien releases before final payment.
- Code compliance. The permit is in the owner's name, so the owner answers for work that fails inspection.
What happens if the rules are broken
Under the statute, if the owner-builder requirements are violated, the local permitting agency must withhold final approval, revoke the permit, or pursue action for unlicensed activity against the owner and anyone doing licensable work. Under section 489.127, an unlicensed person who starts work requiring a permit without the permit in effect commits a first-degree misdemeanor, and repeat violations or violations during a declared state of emergency are third-degree felonies. A separate rule bars licensed contractors from letting their license number be used by someone else or from pulling a permit without a contract for the work.
Questions people ask
Can I hire subcontractors on an owner-builder permit?
You can hire licensed contractors for work within their licenses. You cannot hire an unlicensed person to act as a contractor or supervisor. The county and state disclosure points both stress that the owner must verify each license. See how to hire a licensed general contractor.
Can I take over a permit after my contractor stops work?
Section 553.79(16) of the statutes says a property owner may close a permit by hiring the original or another licensed contractor, or by acting as an owner-builder. A replacement contractor is not liable for the original contractor's defects. The completion route in section 489.103(7) requires the local agency's approval and a finding that the project was substantially complete.
Does the exemption apply to a house I plan to sell?
Not if it was built for sale or lease. A sale or lease within one year of completion creates the statutory presumption described above. Ask a real estate attorney about your specific plans.
Check before you decide
- Confirm with the permitting agency which version of the owner-builder limits it applies.
- Price the owner's role honestly: daily on-site supervision, scheduling inspections, payroll duties if you employ anyone.
- Confirm who will hold each trade permit.
- Ask your insurance agent how a project you manage yourself affects coverage.
- Compare the cost of the exemption with hiring a licensed contractor, which moves permit responsibility to that contractor.
For larger projects, a licensed firm handles permitting and inspections through general contracting.