Roof replacement process in Miami-Dade, step by step

How a roof replacement runs in Miami-Dade: inspection, permit, tear-off, dry-in, covering, final inspection, and the warranty paperwork to collect.

By AV Construction Group Corp. Published 7 min read

Illustration for articles about roofing

A roof replacement in Miami-Dade follows a set order: inspection and written scope, product selection, permit, tear-off and deck check, dry-in with underlayment, the roof covering, and a final inspection that closes the permit. The county inspects at several stages, not only at the end. You finish by collecting the permit record, the warranty documents, and proof that subcontractors and suppliers were paid.

Step 1: Inspection and written scope

The process starts with a roof inspection that records the roof type, approximate area, slope, deck condition where visible, flashing, and penetrations such as vents. From that, the contractor writes a scope: what comes off, what goes on, and what happens if rotten deck is found.

Ask how deck repair will be priced, because it is hard to see until the old roof is off. See what drives the price of a roof replacement for how to compare that line item between bids.

Step 2: Choosing the roofing system

Roofing in Miami-Dade falls under the High-Velocity Hurricane Zone (HVHZ) provisions of the Florida Building Code, and the County's guide ties roof permits to HVHZ forms and Miami-Dade product approval. The County's e-permitting guide states that only current Miami-Dade Notices of Acceptance (NOA) are accepted there, and that tile jobs need NOAs for the tile, the underlayment, and the adhesive or mortar if tiles are adhered. Products and components are chosen as an assembly, so ask for the NOA numbers in the proposal. Roof permit and product approval rules explains how NOAs work.

Step 3: Permit

The roofing contractor applies for the permit. In the County's online system for unincorporated Miami-Dade, the applicant enters a license number that is checked for current license and insurance, and the homeowner's signature is not required. That guide dates from 2018, and cities within the county run their own permit offices, so your city may use different steps. The guide says commercial re-roofing permits cannot be obtained through that system.

Two items matter to owners:

  • Notice of Commencement. The guide and inspection checklist call for a recorded Notice of Commencement on jobs over $2,500.
  • Owner's Notification Form. The inspector collects the County's owner's notification form at the first inspection.

On the code edition: Miami-Dade's notice says the Florida Building Code 9th Edition (2026) takes effect December 31, 2026, and applications submitted on or after that date must follow it. The notice sets a 4 PM cutoff on December 30 for online portal submissions, which is slightly inconsistent with that effective date, so confirm timing with the department if your permit falls near it.

Step 4: Tear-off and deck check

After the old roof is removed, the deck is exposed and can be inspected. For roof replacement on site-built single-family homes, Section 553.844 of the Florida Statutes says the replacement must incorporate techniques for strengthening roof deck attachment and for a secondary water barrier. Roof-to-wall connection upgrades apply only under conditions the statute spells out, including a home in the wind-borne debris region with an insured value of $300,000 or more, and cost limits. Ask the contractor how these rules apply to your house.

The County's roof inspection checklist lists sheathing re-nailing among the items the inspector verifies. Rotted deck boards get replaced before dry-in, which is why the scope should say how replacement is billed.

Step 5: Dry-in

Dry-in means the deck is covered with underlayment and flashing so the house is protected until the final roof covering goes on. For roofs with slopes of 2:12 and greater, the County's summary of the 2023 HVHZ roofing changes (effective January 1, 2024) allows one of three underlayment methods:

  • Self-adhering polymer-modified bitumen over the entire deck
  • Tape or sealed strips over deck joints, then an approved underlayment, with double coverage required below 4:12 slope
  • Two layers of nailable underlayment, fastened as the document specifies

Secondary water barrier underlayment in Florida explains the purpose. Inspections in this stage are described next.

Step 6: Roof covering and flashing

The covering is installed according to its NOA and the manufacturer's instructions. Flashing details, such as edge metal, valley metal, and counter flashing, are where inspectors look closely. Edge metal, valley metal, and counter flashing appear on the shingle and tile checklists.

The inspections, stage by stage

The County's roof inspection checklist lists these inspection types, with the system-specific items they cover. Names and codes may change, so treat this as a guide to what to expect.

StageWhenTypical items
Before anchor sheet or underlayment is coveredDuring or after underlaymentRe-nailing, underlayment, fasteners, edge metal, valley metal, flashing, Notice of Commencement
Installation inspectionWhile shingles, metal panels, or tile are going onSlope, fasteners per NOA, starter course, penetrations, counter flashing
Cap sheet and tile placement (tile roofs)During those stepsCap sheet laps, tile attachment, foam or adhesive per NOA
FinalAfter roofing work is completeCompleted installation, penetrations, edge metal, counter flashing, equipment

For adhesive-set or mortar-set tile, the checklist requires a static uplift test before final. The permit holder, not the owner, requests inspections and should check the work first. Inspectors list deficiencies, and a failed inspection means a re-inspection after correction.

Step 7: Final inspection and closeout

The permit is closed only when the final inspection passes. Before making final payment, gather:

  1. The approved final inspection record or permit status
  2. Copies of the NOAs used on your roof
  3. Manufacturer and workmanship warranty documents
  4. The contractor's final payment affidavit and any lien releases

Under Section 713.06 of the Florida Statutes, the contractor must give the owner a final payment affidavit when final payment is due, stating that those who gave proper notice have been paid or listing who has not. The owner is told to hold final payment until it is furnished. This is not legal advice; see construction liens in Florida for an overview.

Understanding the warranty paperwork

Roofs usually have two warranties. The manufacturer covers the product. The contractor covers installation. An FRSA article from 2019 notes that manufacturer warranties often exclude storm damage, ponding water, and installation by an unauthorized roofer, and that installation warranties typically exclude poor maintenance and normal wear. NRCA advises reading the warranty closely, including what voids it. Ask who registers the warranty, whether it transfers if you sell, and what maintenance it requires.

Questions people ask

Who schedules the inspections?

The permit holder does. The County's checklist says the permit holder must inspect the work and confirm code compliance before calling for an inspection.

Does the roof need to be dry-in inspected before the covering goes on?

The checklist lists an inspection while the underlayment or anchor sheet is exposed. Ask your contractor to show you the inspection record for that stage.

What if the inspector finds a problem?

Deficiencies are listed, corrected, and re-inspected. Ask how the contractor handles that, and whether the contract allows final payment before the permit closes.

Check before you decide

  • The proposal names the roofing system and its NOA numbers.
  • The permit is pulled in the licensed contractor's name before work starts.
  • Deck repair is priced per board or per square foot, in writing.
  • You have the final inspection record, NOAs, warranties, and affidavit before paying in full.
  • Rules and editions change; confirm with your building department.

Sources

  1. Miami-Dade County: Roof inspection checklist
  2. Miami-Dade County: Guidelines for the Roofing E-Permitting System (2018)
  3. Miami-Dade County: 2023 FBC roofing code changes (HVHZ)
  4. Miami-Dade County: Notice about the Ninth Edition Florida Building Code
  5. Florida Statutes s. 553.844: Windstorm loss mitigation (via Florida Senate)
  6. Florida Statutes s. 713.06: Liens of persons not in privity (final payment affidavit)
  7. FRSA: Warranties, Keeping a Roof Over Your Head (2019)
  8. NRCA: Selecting a roofing contractor